As developers race to scale carbon capture, green steel, sustainable aviation fuel and other clean industrial solutions, insurers are finding themselves at the centre of the transition, helping investors understand and manage unfamiliar risks.
Projects to decarbonise industry often struggle to secure financing. But there is another obstacle that receives far less attention: insurance.
Without adequate cover, banks, investors and customers may be unwilling to back even the most promising low-carbon technologies.
As developers race to scale carbon capture, green steel, sustainable aviation fuel and other clean industrial solutions, insurers are finding themselves at the centre of the transition, helping investors understand and manage unfamiliar risks.
“Bankers won’t lend to anyone if they don’t have clear visibility over how they’re going to get their money back. Insurance gives them a reason to say ‘yes’,” says Charlie Pool, head of carbon advisory at insurance broker Howden, which provides insurance for low-carbon products, from sustainable aviation fuel to carbon credits and carbon capture and storage.
James Schofield, managing director of the Industrial Transition Accelerator, points out that low-carbon projects that are just out of the lab are often funded by venture capitalists, who take on the risks themselves in return for their potential to yield huge financial rewards if they succeed.
But, he adds “you can’t proceed from first-of-a-kind to ‘nth’ of a kind without making your technology insurable”.
Similarly, big projects such as Norway’s Northern Lights carbon capture and storage initiative benefit early on from government subsidies or guarantees that help to derisk projects for investors. But when it comes to scaling up, these risks must be covered by insurers.
For many projects, the risks lie not in the individual technologies being used but in the way that they are integrated with other innovations. The equipment is being put together in new configurations and often in new geographies and new climates.
A clean steel project for example, can involve installing electric arc furnaces, sourcing direct reduced iron and green hydrogen. Or it may involve carbon capture and storage. Not only are many of these technologies not mature themselves, they also lack the accompanying infrastructure – such as CO2 pipelines and storage facilities or hydrogen transportation pipelines – to make them work, both alone and with other technologies.
“Every infrastructure project has a lifecycle – from design to financing, building and operating the asset through to end of life,” says Pool. “There’s a series of tasks to do and every one of those tasks has things that can go wrong. … The role of insurance is to identify those risks, isolate them and transfer that risk to a specialist.”
On CCUS, for example, Howden offers policies that cover the technology risk of facilities failing to perform as promised and counterparty credit risk due to the long-term nature of offtake contracts, as well as policies to cover leaks of CO2 when it is transported and stored.
It is also becoming increasingly important to have political risk insurance to address the challenges of projects in geopolitically volatile regions. With more than 75% of the world’s steel and more than 85% of its cement being produced in emerging and developing markets, that is a particular risk today.
One challenge is getting the data insurers need to identify and price risk, and to assess where claims are likely to arise, and how often. None of this information is available for novel industrial decarbonisation projects, where there is no track record of performance.
As Jatin Sharma, executive vice-president of U.S. insurance broker Amwins, points out: “Insurance operates on the law of large numbers. It can’t provide a solution for something when there is no data.”
But there is innovation in the market to try to address this.
Alistair Moodie is chief product officer of Smart Asset Management Platform (SAMP), a technology startup that has products to help power industry players negotiate better terms with insurers for their assets.
He says even where a particular technology is novel and unproven, all equipment is made of conventional components such as valves and bearings, and the fundamental physics of their behaviour remains the same, regardless of their application.
SAMP connects “a telematics ‘black box’ to plants to provide us with data on equipment that allows us to work out how components are performing, when they are at risk of failing and so reduce that risk,” Moodie says. “We’re seeing sites getting coverage that wouldn’t have otherwise.”
One solar farm has earned back thousands of pounds in premiums in less than a year of policy coverage, he said.
“Insurers are very uncertain about new technologies because they don’t have any feel for the technological risks involved,” he adds.
“By taking a first principles engineering approach that doesn’t rely on historical data, we can help to overcome some of that.”
Insurers can also take comfort from the scale of many of the companies that are building CCUS, sustainable aviation and shipping fuel facilities. These include the energy majors and national oil companies, which have experience in developing complex projects.
A high-quality offtaker with deep pockets and a good credit rating can also get a project over the line, suggests Pool.
“If Google commits to buy power from your project in two years’ time, you can literally take that to the bank.”
The backers of LanzaJet’s Freedom Pines Fuels project, a SAF facility in Georgia in the United States, include Shell, IAG, Microsoft, Mitsui, Airbus, Southwest, ANA and MUFG, heavyweight investors that can support it with offtake, logistics, financing and market credibility, according to the Mission Possible Partnership.
IAG, parent group to airlines including British Airways and Iberia, has also signed an offtake agreement that will help it meet its target of 10% SAF usage by 2030, as well as EU and UK fuel mandates.
Amy Barnes, global head of energy and power at Marsh, says many of the challenges of insuring industry decarbonisation projects as they scale up can be overcome by engaging with insurers at the design stage.
“Often, by the time we’re brought in, many features of the project are already baked in,” says Barnes. “If we’re involved early, we can provide risk advisors who can help to design risk out of the project. For a technology that involves volatile compounds, for example, the insurance industry has a really good understanding of the risks of vapour cloud explosions – which materials are most volatile, how they should be stored and where. That can be a very low-cost decision during the design phase that becomes a very high-cost impact later on.”
Remedial action to reduce risk might include moving HVAC equipment from the basement to a to a higher floor if a facility is in an area prone to floods, or asking for special measures to protect against wildfires, storm surges or heatwaves, depending on location.
“We are already seeing data centres delayed or cancelled, in part because of issues around the availability of power or water.The insurance industry wants to support early-stage decarbonisation technologies,” Barnes says.
“The key is to engage early.”